BRINGING YOU HOME

Katoomba Landslip Rectification

Scope of Works

The project at Katoomba involved rectification works following a landslide that impacted a residential property. DELT initiated the stabilisation process through detailed geotechnical interventions. Key activities included:

  • Drilling and assessment of rock underpinning bolts (anchors) on site to ensure their effective extension and secure socketing into suitable bedrock.

  • Verification that all inspected rock bolts met the designed serviceability and end bearing capacity as per the specifications outlined in Section 2 of the project report.

  • Continuous monitoring and evaluation based on onsite observations and provided information, to ensure adherence to the structural engineer's requirements.

Location

2024

Sector

Katoomba

Completion Year

Public